November 02, 2012 - More Walls Going Up









October 31, 2012 - Prestress Garage Floor, Walls Started

The Prestress beams for the garage floor were delivered and put in place today.  Framers also started on the upper floor walls.










October 26, 2012 - Flooring and Rough Plumbing

The main floor beams were started today and some of the flooring laid down.  Also, the rough plumbing in the basement was installed.  Roof trusses were also delivered.